INDOT: US 52 Slip Repair Project Will Go Into September

Friday, May 31, 2019 at 10:23 AM

By Indiana Department of Transportation, news release

The project is slated to begin Monday in Franklin County.

(Franklin County, Ind.) - U.S. 52 will close on or after Monday, June 3, weather permitting, between New Trenton and Cedar Grove for emergency slide correction work.

INDOT contractor GeoStabilization International will place a soil nail wall on the east side of the roadway, approximately one mile north of New Trenton. Soil boring will also take place on the west side of the road, along the railroad and Whitewater River.

U.S. 52 will be closed for 90 days and will reopen as one lane with a temporary traffic signal in September. The repair is expected to be complete by late December and the road will open as two lanes at that time.

The official state detour for the closure is S.R. 46 to S.R. 1 to the intersection of U.S. 52/S.R. 1, north of Cedar Grove.

More from Local News


Events

Frost Advisory, Freeze Watch Issued for Tri-State Area

Lows are expected to be near or below freezing the next two nights.

Share Your Thoughts with Five Minute Southeast Indiana Arts & Culture Plan Survey

The survey will shape the Arts and Culture Plan in six SEI counties.

Trick-or-Treat Times in Eagle Country

Halloween falls on Friday, October 31.

Local Players Highlight IHSVCA Academic All-State Team

Twenty-nine local players earned the honor.

Local Sports Report - October 20, 2025

East Central's girls soccer team competed at the regional round.

Curtis Eckstein Wins Half Marathon in Columbus

The former OA star can still run.

On Air

Your Hometown Radio Station playing
Tracy Lawrence - Lessons Learned

Little Big Town Pontoon 21:44
Patty Loveless Blame It on Your Heart 21:41
Hardy Favorite Country Song 21:38
Sara Evans Suds In The Bucket 21:32