Milling & Paving Project Continues In Valley Woods Next Week

Work will be done on Persimmon and St. Andrews.

(Greendale, Ind.) – A milling and paving project is rolling on in Greendale.

City manager Steve Lampert says O’Mara Construction is planning to complete milling operations on Persimmon and St. Andrews in Valley Woods on Tuesday, November 10, weather permitting.

Paving is scheduled to be completed the same week between November 11-13.

During paving operations, there will be longer periods of time, likely two to three hours, that the pavement will not be drivable.

O’Mara will have staff in place to direct traffic.

RELATED STORIES

Paving Project Begins Tuesday In Greendale

More from Local News


Events

Local Schools Recognized for High Literacy Rates

Over 400 schools achieved a 95 percent or higher passage rate on the 2025 IREAD.

Indiana State Parks Offers Free Annual Entrance Passes for Foster Families

To get a pass, families need to fill out a short form.

Two Arrested on Drug Charges After Traffic Stop

The arrests occurred on Webers Lane in Franklin County.

Local Sports Report - April 23, 2026

Report missing stats and scores to news@eaglecountryonline.com

EC's Perkins Sets School Record in 200 Meter Dash

The IU commit was on fire on Wednesday night.

Switz. Co. 7th Grader Sets School Record in Shot Put

The record was set at Wednesday night's quad meet in Vevay.

On Air

Your Hometown Radio Station playing
Russell Dickerson - Every Little Thing

Fox News Fox News National Newscast 5:01
Morgan Wallen More Than My Hometown 4:57
Toby Keith and Willie Nelson Beer for My Horses 4:54
Cody Johnson Human - WSCH ONLY 4:50