Phase 2A of the project is set to begin September 8.

(Aurora, Ind.) - According to the Indiana Department of Transportation, Phase 2A of a pavement rehabilitation project on U.S. 50 in Aurora is set to get underway.
Beginning on or after Monday, September 8, crews will begin Phase 2A of the project between State Road 350 and Dutch Hollow Road. Drivers can expect the following traffic restrictions on U.S. 50 through late November, weather permitting.
- All traffic will be shifted to the westbound lanes of U.S. 50 using temporary crossovers while eastbound construction is in progress.
- U.S. 50 will be reduced to 35 mph and an 11-foot lane width reduction will be in effect.
Additional traffic shifts will take place while overall work is in progress. INDOT will continue to provide information and updates as work progresses.
Overall work is expected to be complete in spring 2026, weather permitting. Overall work was previously scheduled to be complete in November 2025. The schedule has been modified due to additional required work and weather impacts. Initial project information can be found here.
This work is part of a $8.7 million contract awarded Paul H. Rohe in February 2025. INDOT reminds drivers to slow down, use extra caution, and avoid distractions when traveling in and near work zones. All work is weather-dependent and schedules are subject to change.

Traffic Switch on I-275 Eastbound Carroll Cropper Bridge
Indiana Court of Appeals Affirms Billy Luke's Sentence of 61 1/2 Years
State Park Properties Offer First Day Hikes on New Year’s Day
Repairs Underway After Water Main Break in Dillsboro
DCF Grant Helps Church Purchase Defibrillator
RCCF Awards $22,000 In Hillenbrand Partner with Possibility Grants

