Crews Entering Final Phase of Work on Carroll Cropper Bridge

Floor beam repairs are the last task to complete.

(Petersburg, Ky.) - The final phase of the I-275 Carroll Cropper Bridge project is scheduled to get underway this week. 

As of last Friday, the scaffolding plan for the bridge has received final approval. Starting this week, crews will begin installing scaffolding to prepare for floor beam repairs, weather permitting. 

Once these repairs officially begin, the Kentucky Transportation Cabinet will provide another update with a revised completion date for the overall project. As of now, the completion date is Fall 2025 with no specific date mentioned. 

As of September 10, crews completed all four expansion joint repairs. T-1 steel repairs have also been completed. 

For more information on the project, visit Carroll Cropper Bridge | Driving NKY Progress.

 

More from Local News

Events

Healthy Zzz’s Sit N’ Sleep Named Greater Harrison Business of the Year

The Greater Harrison Chamber will hold their annual awards celebration on Nov. 13.

Crews Entering Final Phase of Work on Carroll Cropper Bridge

Floor beam repairs are the last task to complete.

Eli Aston Earns HCAC Week 3 Offensive Player of the Week

The former EC Trojans continues to put up big numbers on the college football field.

Local Sports Report - September 22, 2025

Report missing stats and scores to news@eaglecountryonline.com

Batesville's Zimmerman Records 1,000th Career Kill

She is committed to Florida International University.

On Air

Eagle Country 99.3 playing
Patty Loveless - I'm That Kind Of Girl

Tyler Hubbard and Tim McGraw Undivided 10:29
Craig Morgan Redneck Yacht Club 10:25
Alabama Feels So Right 10:22
Rodney Atkins Take A Back Road 10:18