Milton-Madison Bridge Span Lift Sept. 10

Press release from Milton-Madison Bridge Project

 

The Milton-Madison Bridge over the Ohio River.

file photo

(Madison, Ind.) - The Milton-Madison Bridge Project is expected to mark another major milestone next week when a second massive section of the new bridge is lifted into place. The 727-foot preassembled section of steel truss will be hoisted onto temporary piers, another in a series of steps to replace the US 421 bridge, connecting Milton, Ky., and Madison, Ind.

 

The existing bridge remains open during the lift, currently scheduled to begin at 12:00 a.m. on September 10, weather permitting. The span, which was preassembled on barges in Milton, will be floated into position and lifted using a method called “strand jacking,” often used to lift heavy structures.

 

Special hydraulic jacks and bundled strands of steel cable will lift the 2,067-ton span to a height of 90–95 feet onto temporary piers 4 and 5, immediately north of the first section that was lifted in June.

 

Because the span lift takes place in the main navigational channel, the river will be closed to commercial traffic for approximately 24 hours. The U.S. Coast Guard will determine when the river can safely reopen. Recreational boaters will also be prohibited from using the area near the lift during this time. A “no wake” zone will be established 1,000 feet upstream and downstream of the bridge, and boats must stay back 500 feet on either side of the bridge. For the safety of the boaters and the workers, this restricted area will be enforced. 

 

Once the span reaches its full height, a “sliding girder” will be placed under the truss, supported by the temporary pier and a concrete pedestal on the existing piers. This massive beam will be used next spring when the completed 2,426-foot bridge slides from its temporary position onto the permanent piers, which are being rehabilitated and strengthened.

 

The new bridge is currently scheduled to open to traffic in spring 2013.

More from Local News

Events

Southeastern Indiana Art Guild Hosts Regional Summer Art Show

The art show is running now through August 16.

UPDATE: Work Continues on State Road 7 in Jennings County

State Road 7 to open to one lane, temporary traffic signals to be activated.

Developer Sought to Transform Former School Building into Mixed-Use Community Asset

The SDCSC Board voted to close Moores Hill Elementary School in 2021.

East Central Girls Basketball Enjoys Stellar Summer

The Lady Trojans won a bunch of games and had five players invited to a prestigious event.

Local Sports Report - August 4, 2025

Report missing high school stats and scores to news@eaglecountryonline.com

IFCA Releases Preseason Top 10 Polls

Three area teams will start the high school football season ranked.

On Air

Your Hometown Radio Station playing
Miranda Lambert - It All Comes Out In The Wash

Vince Gill What The Cowgirls Do 2:19
Sam Hunt Water Under the Bridge 2:16
Mel McDaniel Baby's Got Her Blue Jeans On 2:13
Corey Kent This Heart 2:09