I-275 Bridge Deck Overlay To Start In April

Monday, February 4, 2019 at 11:49 AM

By Indiana Department of Transportation, news release

The work will be done just north of U.S. 50 in Lawrenceburg.

(Lawrenceburg, Ind.) - Indiana Department of Transportation officials met with contractor representatives this week (JAN 30) at Seymour District offices to discuss operations for overlaying bridge decks on twin Interstate 275 structures located 1.34 miles north of U.S. Highway 50 at Lawrenceburg. Work is scheduled to begin on or after April 1.

Dave O’Mara Contractor, of North Vernon, will hydro-demolish the current driving surface atop 3-span 146-foot-long twin bridges that overpass Action Lane, an access road just north of Belleview Drive, and replace them with 2½-inch-thick concrete deck overlays. This $1,744,288 bridge project includes new concrete bridge rails, approach slabs and guardrail.

Traffic will be restricted to a single lane on both northbound and southbound I-275 bridges. The speed limit will be reduced to 55 mph. 

The contract completion date is October 31.

I-275 has a traffic count of 16,110 vehicles per day.

 

More from Local News

Comments

Add a comment

Log in to the club or enter your details below.
Rating *

Events

Ripley Co. Health Department Confirms One Measles Case

Community members are encouraged to receive the MMR vaccine.

Switzerland County Golf Star Will Tee It Up at IU Southeast

Alexis Mangold has made her college choice after an incredible high school career.

East Central Lands on IBCA, ICGSA Polls to Start 2026-27 Season

The Lady Trojans have a ton of talent back from a team that won 21 games last season

OA's Hautman Receives Mental Attitude Award at State Championship

Ryan Hautman is a tremendous goalkeeper who also excels in the classroom

On Air

Eagle Country 99.3 playing
Lee Ann Womack - I Hope You Dance

JD SHELBURNE Every Little Town 11:45
Jason Aldean Take A Little Ride 11:41
Sara Evans Suds In The Bucket 11:37
Craig Morgan Bonfire 11:34