Floor beam repairs are the last task to complete.

(Petersburg, Ky.) - The final phase of the I-275 Carroll Cropper Bridge project is scheduled to get underway this week.
As of last Friday, the scaffolding plan for the bridge has received final approval. Starting this week, crews will begin installing scaffolding to prepare for floor beam repairs, weather permitting.
Once these repairs officially begin, the Kentucky Transportation Cabinet will provide another update with a revised completion date for the overall project. As of now, the completion date is Fall 2025 with no specific date mentioned.
As of September 10, crews completed all four expansion joint repairs. T-1 steel repairs have also been completed.
For more information on the project, visit Carroll Cropper Bridge | Driving NKY Progress.

INDOT Makes Changes at Busy Lawrenceburg Intersections
Water Tie-in Project Impacting Water Pressure for Greendale Residents
Community Resource Day Connects Families with Local Resources and Summer Fun
Gov. Braun Declares State of Disaster Emergency for 63 Indiana Counties
New Trail Opens Connecting Clifty Falls State Park to Madison’s Riverwalk
RCCF Welcomes Brady Westerfeld as Grants Manager