Pavement, Bridge Replacements to Close U.S. 421 near Napoleon and Osgood Next Month

Tuesday, March 8, 2022 at 12:15 PM

By Indiana Department of Transportation, news release

The project is slated to start on or after April 1.

Shutterstock photo.

(Ripley County, Ind.) - Indiana Department of Transportation contractor Dave O'Mara Contractor Inc. plans to close U.S. 421 in early April to begin work on two construction contracts, totaling nearly $7 million in Decatur and Ripley Counties. Work includes pavement replacement between Napoleon and Osgood, and bridge replacements over Vernon Fork Muscatatuck River and Laughery Creek.

Pavement Replacement -  U.S. 421 between Napoleon and Osgood On or after Friday, April 1, U.S. 421 is scheduled to close just south of Napoleon for crews to complete pavement removal, patching and replacement. The contractor will work form north to south, closing U.S. 421 in sections. 

  • On/after Friday, April 1: U.S. 421 between C.R. 850 N. and C.R. 750 N. (Section A)
  • Spring/summer 2022: U.S. 421 between C.R. 750 N. and C.R. 600 N. (Section B)
  • Summer 2022: U.S. 421 between C.R. 600 N. and C.R. 450 N. (Section C)

Intermediate paving is expected to be complete in the three sections south of Napoleon by early July. Pavement will also be replaced under closures between Wilson Street and C.R. 850 N. in Napoleon. Local access only will be maintained via the north end of each work zone. The south end of each closure will be closed to all traffic. Toward the end of the project, the contractor will complete final surface paving and striping under lane closures with flagging.

Bridge Replacements - U.S. 421 over Vernon Fork Muscatatuck River and Laughery Creek On or after Monday, April 4, Dave O'Mara plans to close U.S. 421 over Vernon Fork Muscatatuck River in Decatur County, to complete the first of two bridge replacements. The bridge is located just over five miles north of S.R. 229 (Napoleon) and is expected to remain closed through early July. Construction on U.S. 421 over Laughery Creek in Napoleon is scheduled to begin in July. The bridge is expected to remain closed through late October. Traffic will be directed to the official detour route during all closures (S.R. 229 to S.R. 48 to S.R. 129 to S.R. 350).

Both contracts were awarded to Dave O'Mara last year for a total of $6,990,868.79. INDOT reminds drivers to use extra caution, avoid distractions, and consider worker safety when driving through active construction zones. All work is weather-dependent and schedules are subject to change.

U.S. 421 in Ripley Co.

More from Local News

Events

Lawrenceburg Police Celebrate Retirement of K9 Kilo, K9 Siri

The two K9s combined for over 20 years of service to the community.

UPDATE: Detectives Working to Establish a Motive in NKY Shooting

An individual was located early Tuesday morning along I-275 suffering from a gunshot wound

Indiana State Police Partners with DEA for Drug Take Back Day

Unwanted, unused or expired medications can be dropped off for proper disposal

Batesville Girls Win Cross Country Sectional Title

Several boys and girls teams and individuals are advancing to regionals.

Sectional Champs Crowned, Seasons End for Area Volleyball Teams

See who is moving on in the IHSAA State Tournament

Switz. Co. Advances to Semi-State with Hard-Fought Regional Title Win

The Lady Pacers will face a Top 5 opponent at Semi-State

On Air

Sara Evans Born To Fly 23:28
Rodney Atkins Caught Up In The Country - EAGLE ONLY 23:25
Faith Hill Someone Else's Dream 23:21
kelsey Hart Life With You 23:18