I-275 Bridges Close To Finish Road Work

Intermittent lane closures planned Monday and Tuesday on I-275 bridges in Dearborn County.

(Dearborn, Co.) - INDOT announced that Dave O'Mara Contractor Inc. will be conducting intermittent lane closures next Monday and Tuesday, October 28 and 29. 

Both lanes reopened with temporary markings this past Wednesday.  

The north and southbound I-275 bridges over Action Lane in Dearborn County will be closed throughout Monday and Tuesday to complete permanent pavement marking application. 

October 31, was the scheduled end date for the $1.7 million bridge deck overlay project. The project includes new bridge rails, approach slabs and guardrail for both bridges.

Crews could be in the area removing signs and other equipment past the 31st. 

Motorists are reminded to slow down, use extra caution and drive distraction-free when traveling in and near all work zones.

More from Local News


Events

Stoneking Named Batesville High School Principal

The appointment is effective July 1.

Green Alert Issued for Burlington Man

The man is considered armed and dangerous.

Indiana Governor Declares Gas Tax Holiday to Save Money for Hoosier

Governor Braun's gas tax holiday is a 30-day suspension of the 7% usage tax on fuel.

Local Sports Report - April 7, 2026

Report missing stats and scores to news@eaglecountryonline.com

Milan's Norman Selected for Top 60 Senior Workout

Unfortunately, he will not be able to participate due to injury.

Local Sports Report - April 6, 2026

Report missing stats and scores to news@eaglecountryonline.com

On Air

Chelsie playing
George Strait - Gone As A Girl Can Get

Luke Combs When It Rains, It Pours 7:34
Florida Georgia Line I Love My Country - EAGLE ONLY 7:28
Lacy J. Dalton 16th Avenue 7:25
Faith Hill Take Me As I Am 7:19