Work is scheduled the rest of this week and early next week, weather permitting.

Photo by Travis Thayer, Eagle Country 99.3.
UPDATE: No asphalt paving today, September 30th - due to a mechanical failure at that asphalt plant. Parking CAN resume on all streets for today. Further updates on the paving schedule will be sent later this afternoon. Further updates are expected to be released later today.
(Lawrenceburg, Ind.) - Asphalt paving operations will begin today in downtown Lawrenceburg.
The paving schedule is as follows, weather permitting:
- 09/30: Walnut St from US 50 to Center St.
- 10/01: Walnut St from Center St to New St.
- 10/02: Short St & High St.
- 10/05: High St.
These streets will experience intermittent closures and there will be no street parking during paving operations. Parking can resume once no parking signs are removed.
For construction updates see https://thinklawrenceburg.com/construction-information/

Gov. Braun Continues Suspension of Gas Tax, Delivers New Relief for Farmers
The Wildcat Haven: A Safe Space for Students and Staff to Focus on Mental Health
Former RCCF Intern Selected as Ripley Co. Ambassador at Ball State
Margaret Mary Health Recognizes DAISY and BEE Award Winners
KSP Makes Arrest of Armed Man on School Property in Trimble County
ISP Detectives Investigating Franklin County Shooting