Construction Project To Begin On S.R. 129 Next Week

Traffic will be managed by lane closures with flagging. 

Shutterstock photo.

(Ripley County, Ind.) - An asphalt resurfacing project on S.R. 129 south of Batesville will begin on or after June 28. 

The $2.4 million contract will begin with crews patching between S.R. 48 and S.R. 46. 

Milling and paving are anticipated to begin around mid-July, with the project completion expected by the end of August. 

Traffic will be managed by lane closures with flagging. 

Drivers should drive slow, cautious and distraction-free in and near the construction sites. 

The project is weather dependent and schedule is subject to change. 

Map provided by IDOT

More from Local News

Events

State Line Road to Close for Slip Repair

The closure is due to a slip repair project.

Box Culvert Installed on U.S. 52; More Work Ahead in Franklin Co.

The project is scheduled to run through early October.

Record Low Temperature Recorded at CVG

The previous record low for August 27 was 50 degrees.

Local Sports Report - August 26, 2025

Report missing stats and scores to news@eaglecountryonline.com

Greendale Middle School Boys Cross Country Team Earns 2nd Place at Greensburg Invitational

One of the largest middle school cross country events in the state.

On Air

Eagle Country 99.3 playing
Vince Gill - One More Last Chance

Scotty McCreery Feelin' It 13:18
Caylee Hammack Family Tree 13:09
Radney Foster Nobody Wins 13:06
Preston Cooper Weak 13:02