Patching efforts will last about two weeks, but milling and paving will last through the summer.

Shutterstock photo.
(Franklin County, Ind.) - Indiana Department of Transportation contractor Paul H. Rohe Company plans to begin patching work next week along S.R. 46 between Greensburg and Batesville in Decatur and Franklin Counties. Patching is expected to take approximately two weeks and will require various lane closures and flagging.
Following patching, crews will begin milling and paving the 13.5-mile section of roadway between U.S. 421 and S.R. 229. Work will continue throughout the summer under additional lane closures.
The $3.4 million contract was awarded last October and is scheduled to be complete by the end of August. Motorists are reminded to slow down, use extra caution, and drive distraction-free in and near work zones. All work is weather-dependent and schedules are subject to change.


Queens Court, 4-H Royalty Crowned at 2026 Dearborn County Fair
Search Continues for Missing Franklin Co. Teen
Genesis: Pathways to Success Brings Imagination to Life Through Summer Camps
Indiana Unemployment Rate Steady in May
West Chester Man Loses 132 Pounds, Named 2025 TOPS Indiana King
Franklin County Deputies Complete Crisis Intervention Team Certification