This project was previously delayed from April 1.

(Ripley Co., Ind.) - A deck replacement project will begin on State Road 101 in Ripley County starting next week.
On or after Monday, June 1, INDOT contractor Force Construction will begin work on the bridge over South Hogan Creek.
For approximately 90 days, the State Road 101 will be closed south of Milan between County Road 50 N and County Road 50 S.
The official detour for the closure will follow State Road 350 to State Road 129 to U.S. 50.
The contract was awarded to Force Construction and is expected to be complete by September 30.