The project is expected to be completed June 2024

Shutterstock photo.
(Covington, Ky.) - The Kentucky Transportation Cabinet (KYTC) District 6 Office announces lane closures on I-275 in Boone County beginning Sunday, Aug. 27, as part of a resurfacing project.
Crews will be working on I-275 between the Boone/Kenton County line (mile point 1.58), to west of the KY 237 (Hebron Exit) at the 7.25 mile point, a distance of 5.67 miles. The project will include partial/full-depth concrete patching and diamond grinding. Additionally, the KY 3076 (Mineola Pike), KY 212 (Airport Access Road), and KY 237 (Hebron) on/off exit ramps will be resurfaced.
During ramp work, traffic on the exit ramps in the project area will be maintained at partial-width (11 ft. minimum) lanes. The project will require the off-ramp from I-275 westbound to KY 212 (Airport Access Road) to be temporarily closed on pre-approved scheduled weekends. KYTC will make an announcement via updated press release/social media ahead of the closure to keep motorists informed, and provide detour information during the closure.
Weather permitting, beginning Sunday, Aug. 27, road crews will shift I-275 westbound traffic in the project area to the inside shoulder to begin addressing partial-depth patch work.
Traffic may be reduced to one lane in each direction during the following times:
- Weeknights from 9 p.m. to 5 a.m.
- Weekends from 9 p.m. Friday, until 5 a.m. the following Monday.
The contractor will maintain a minimum of two lanes of traffic in each direction at all other times.
Work on the project will be performed in phases. These phases include milling/resurfacing of asphalt exit ramps, removing/replacing pavement, diamond grinding, saw/seal joints and placing permanent striping and pavement markers.
The main benefits of properly using diamond grinding include a smoother ride, reduced road noise and improved friction.
No work will occur on the following days:
- Labor Day Weekend (Sept. 1-4)
- Thanksgiving Weekend (Nov. 23-26)
- Christmas Weekend (Dec. 22-25)
- New Year’s Weekend (Dec. 29, 2023 – Jan. 1, 2024)
- Martin Luther King Jr. Day Weekend (Jan. 12-15, 2024)
- Easter Weekend (March 29-31, 2024)
- Memorial Day Weekend (May 24-27, 2024)
Please drive carefully through the project area. Motorists are advised to find an alternate route during working hours.
KYTC has been in communication with the Cincinnati/Northern Kentucky International Airport (CVG), Boone County Emergency Management and other first responder agencies ahead of the upcoming resurfacing project.
The $4 million project was awarded to Eaton Asphalt of Walton, KY. The project is expected to be completed by June 30, 2024.

Student Entrepreneurs Pitch Big Ideas at 2025 D.I.C.E. Challenge
DCF Board Member Selects River Valley Resources for Proactive Grant
AAA Projects Record Travelers for 13-Day, Year-End Travel Period
Harrison City Council Approves Target Project
Merritt Alcorn Recognized for Decades of Service to South Ripley Schools
Batesville Intermediate School Art on Main Focuses on Emotions