INDOT: US 52 Slip Repair Project Will Go Into September

Friday, May 31, 2019 at 10:23 AM

By Indiana Department of Transportation, news release

The project is slated to begin Monday in Franklin County.

(Franklin County, Ind.) - U.S. 52 will close on or after Monday, June 3, weather permitting, between New Trenton and Cedar Grove for emergency slide correction work.

INDOT contractor GeoStabilization International will place a soil nail wall on the east side of the roadway, approximately one mile north of New Trenton. Soil boring will also take place on the west side of the road, along the railroad and Whitewater River.

U.S. 52 will be closed for 90 days and will reopen as one lane with a temporary traffic signal in September. The repair is expected to be complete by late December and the road will open as two lanes at that time.

The official state detour for the closure is S.R. 46 to S.R. 1 to the intersection of U.S. 52/S.R. 1, north of Cedar Grove.

More from Local News

Comments

Add a comment

Log in to the club or enter your details below.
Rating *

Events

Area High School Students Learn About Legal Field During Leadership and Law Week

The program was created nearly 20 years ago in Dearborn County.

Retired Lawrenceburg Police Lieutenant Passes Away

Our condolences to the Hoffman family

Scottsburg Claims Sectional 29 at Sunrise

See who else advanced to the regional

Batesville Go Back-to-Back as Sectional Champs

Sectional 28 was held at Greensburg Country Club.

Local Sports Report - June 5-6, 2026

Track & Field State Finals, Softball Semi-State, Baseball Regional, and Boys Golf Sectional results.

On Air

Chelsie playing
Josh Turner - Time is Love

George Strait The Chair 6:42
Oak Ridge Boys American Made - EAGLE ONLY NO INTRO IMAGING 6:35
Mark Wills Wish You Were Here 6:31
Brooks & Dunn Ain't Nothin' About You 6:26