(Batesville, Ind.) - Huntersville Road is open.
INDOT Southeast has announced the bridge replacement project over I-74 in Batesville is mostly complete. Crews will return to complete minor punch list work.
Huntersville Road had been closed since the spring and the original completion date of late August was pushed back to mid-November due to project material adjustments.
This work was part of a $2.6 million contract awarded to Sunesis in September 2024.